Time-Lag-Aware Deep Reinforcement Learning for Flexible Job-Shop Scheduling in PPVC Module Factories
Prefabricated prefinished volumetric construction moves most building work into module factories, whose production floor operates as a flexible job shop. A major complication is decisive: long post-operation time-lags caused by concrete curing, watertightness ponding tests, and paint drying, during which a module is blocked while its workstation stays free. On benchmark instances grounded in an official national prefabrication guidebook, these lags inflate even the optimal reference makespan by about 67% on average, and ignoring them at decision time, then repairing to feasibility, is worse th